Sept. 17th: 2nd Story and Stairs

Sept. 18th: 2nd floor framed

Sept. 19th: Roof


Sept. 24th: Plumbing and Bath Tubs


Sept. 27th: Gas Line and Furnace


Oct. 1st:  Electricity


Oct. 2nd: Back Shingles

Oct. 3rd: Front Shingles, Windows,and Wrapping

Oct. 5th: Insulation and Front Door


Things are moving right along.  We are starting to get antsy.  Hopefully we will be able to move in before Thanksgiving.  

1 comment:

Sarah said...

I am so excited for you guys!! It is looking great! Plus it will be fun to have these photos as memories in years to come.